Empennage kit closing inspection

Monday night, Andi Portner, our tech counselor stopped by for the closing inspection on the empennage kit. This step is a requirement in order to get final approval once the aircraft is completed.

In order to inspect the rivet lines, we had to un-cleco the rear spars...

Andi completing the inspection report. He gave us compliments for very good work which makes us quite proud :-)

The same night, we dimpled the elevator skins, so that they are ready for the first primer-session. Only the holes where the stiffeners / trim reinforcement plate will mount have been worked on so far.

 